BOS-PRD-07.900607

When a synthetic mooring rope is turned up on a set of bits, two round turns

shall

be made around the

leading post of a large set of bits or around both posts for smaller circumference posts before starting to

figure of eight the rope.

When a wire rope is turned up on a set of bits, three round turns

shall

be made around the bits before

applying four figure of eight turns. The top layers

shall

be lashed to prevent them jumping off.

The method of turning up wire and ropes as described in 6.5 and 6.6 allows greater control of the rope when

slacking down or transferring to a drum end as it reduces the possibility of a sudden surge as the turns on

the bits are reduced.

When fastening a brake to make a line fast it is often difficult to manually tighten brakes to their maximum

extent when a mooring line has little load on it. People of different physical strength

shall

apply different

forces to the winch brake lever. For this reason the winch brakes

shall

be checked at frequent intervals as

changes in load on the mooring line, due to changes in height of tide or free board, may cause a

redistribution of stresses in the brake band allowing the brake to be applied further.

On ships fitted with hydraulic brakes, the torque setting indicator

shall

be marked with the setting required for

optimum brake application. This figure

shall

be obtainable from the manufacturer’s operation manual.

In order to conform with local regulations, rat-guards

shall

always be placed on all mooring lines.

De

c

k

Off

i

c

ers

shall

, as part of their harbour duties ensure that the rat-guards remain in place.

4

.

2

.

8

T

en

d

in

g

o

f

m

oorin

g

w

h

en alon

g

si

d

e

During the period alongside the moorings

shall

be regularly inspected and tended if required. The manning

required to tend the mooring

shall

be decided by the

Master

. The level of manning required

shall

of course

depend upon the design of the mooring system such as all the lines are on winches, or if some are turned up

on bits and the amount of tending expected throughout the time alongside.

While alongside, the bridge have to be manned at all time, in order to ensure that unpredicted changes in

environmental conditions and traffic movements are monitored and recorded in the

Bridge Logbook

to

prevent the vessels breaking out from her moorings.

4

.

2

.

9 T

h

e

u

n

b

ert

h

in

g

o

p

eration

The

Master

is responsible for ensuring that sufficient personnel are assigned to each mooring station.

Prior to the unberthing of the ship, the

Master

is to discuss with the

Pilot

the procedure for letting go. The

Master

shall

instruct the Officers or other persons responsible for the fore and aft mooring stations. The

instruction

shall

include:

x

Safety precautions to be observed during the operation;

x

The use of any tugs, their position and means of making fast;

x

Sequence of letting lines go;

x

The need to report when the propeller and thrusters are clear.

The un-berthing operation

shall

not commence until all essential bridge and engine room systems have been

checked and reported as satisfactory.

The singling up operation

shall

be carried out in an orderly fashion. Any line brought in

shall

be clear of the

working area before another line is worked.

The person supervising the operation

shall

observe that the lines do not snag any obstructions on the shore

or jetty or present a danger to any small boats in the vicinity.

Version 04. Original date: 22/06/2012. Version date: 31/12/2014. Valid version only on QMS site. Uncontrolled document when printed.

Procedure prepared by: BOS Operations Department Project Coordinator. Approved by: Head of Operations. Validated by: BOS Quality Representative