BOS-PRD-07.900611

4.1.1.3 Helicopter hoisting team

The helicopter hoisting team

should

be composed as follows:

-

Master

-

Ch

ie

f Off

icer

in charge of the operation on the Hoist Zone.

-

Bos

u

n

and

AB

s in charge to assist the

Ch

ie

f Off

icer.

a.

Ch

ie

f Off

icer

The

Ch

ie

f

Off

icer

should

wear a reflecting jacket (clearly identifiable by the pilot) along with the following

PPE: gloves, safety glasses, and radio-equipped hearing protection (or alternatively hearing protection and a

radio equipped with a microphone).

The

Ch

ie

f Off

icer’s

duties are to:

- direct the activities of the

Bos

u

n

and

AB

s.

- give regulatory aircraft hand signals (UKOOA).

The

Ch

ie

f Off

icer

must be able to receive and provide information to the

W

atc

h Off

icer

either directly or via

a signaller.

b.

Bos

u

n an

d

ABs

The

Bos

u

n

and

ABs

will tend to hooking and unhooking the stretcher or other loads.

Bos

u

n

and

ABs

should

wear the following equipment:

- coveralls;

- hard hat with chin strap;

- safety glasses;

- gloves;

- safety shoes.

They

should

also be equipped with a static discharge rod.

4

.1.

2 V

essel

p

re

p

aration

b

e

f

ore arri

v

al o

f

t

h

e

h

elico

p

ter

4.1.2.1 Hoist zone

Regardless of the chosen location, the hoisting zone must be clear. Any antennas that could snag the hoist

cable

should

be lowered and any loose material that might be blown about by the rotor downwash

should

be

removed.

The Vessel

Master

can override this requirement if he/she deems that railings and safety nets must be

maintained in a raised position to ensure the safety of operational personnel (e.g. in case of significant

vessel movement, slippery deck, or windy conditions).

The helicopter pilot is responsible for the safety of his/her aircraft. He/she must be informed of any potential

hazards in the hoisting zone and retains the right to make the final decision on whether or not to carry out the

hoisting operation.

4.1.2.2 Fire-fighting team

A fire-fighting team must stand by in a safe location near the hoisting zone. They

should

be equipped with

two fire-hoses (or mobile foam extinguishers) for simultaneous use on the starboard and portside.

4.1.2.3 Rescue boat crew

The rescue boat (work boat or FRC) must be ready for immediate launching.

Version 01. Original date: 08/08/2014. Version date: N/A. Valid version only on QMS site. Uncontrolled document when printed