Page Background

Met

h

anol

Op

erations

BOS-PRD-07.900609

Bravo flag

shall

be shown and red light in the mast at night.

Sea water

should

never be used in cofferdams or methanol tanks to reduce corrosion development. Drill

water, fresh water

should

be used instead.

All escape hatches and doors from Main deck into Propulsion Room, Stores and Accommodation

shall

be

kept closed as soon as methanol is started to be loaded on board

4

.

2

.

2 T

ank

p

re

p

aration

PV valves

shall

be inspected. PV valves shall be left in automatic to maintain a slight positive pressure inside

the tanks at all times.

Methanol tanks manholes are accessible through the cofferdam’s access trunk.

Methanol tank access

Complete the PTW enclosed space entry and open cofferdams and methanol tanks manholes.

Test the methanol transfer pump with fresh water, discharge to the bilge well during the test.

Dry the tank with clean rags if necessary.

Check that the high level and very high level (95%) alarms are working suitably.

The client

should

make a survey of the methanol tanks and give his approval for carriage of methanol.

Methanol Tank

Cofferdam

Manholes

Access

Trunk

Version 04. Original date: 22/06/2012. Version date: 31/12/2014. Valid version only on QMS site. Uncontrolled document when printed.

Procedure prepared by: BOS Head of Operations. Approved by: BOS Head of Operations. Validated by: BOS Quality Representative.